Enwave Pearl Street Steam Plant Phase 2 Renovation
 
Location:
Engineer:
Completion:
Mechanical:
Project Type:
Project Value:
Toronto, Ontario
HHAngus Engineering
2017
$2.7 million
Stipulated Sum
$2.7 Million 
 
As the prime contractor, Sprint Mechanical is responsible to install and commission a new 4 MW generator in the existing Pearl Street plant. Our scope of work includes electrical power wiring, structural steel modification, instrumentation, controls and general civil work. All work has been scheduled to maintain full operation of the plant without interruptions to normal operations.