Princess MARGARET hospital cancer lodge diesel upgrade

Location:
Engineer:
Completion:
Mechanical Portion:

Project Type:

Project Value:

Toronto, Ontario
McGregor Allsop
May 2020
$140,000

Stipulated Sum

$140,000 
 

PMH+Cancer+Lodge+Diesel.jpg

This project consisted of installing a new main tank and a new day tank to the existing diesel generator complete with new fuel pump, piping, electrical, controls and new service platform. Commissioning of the project included a first fill, TSSA inspection, an OBT-1 inspection and a load bank test. As the prime contractor, Sprint was also responsible for the installation of the new chain link fence and bollard to protect the tank.