Princess MARGARET hospital cancer lodge diesel upgrade
Location:
Engineer:
Completion:
Mechanical Portion:
Project Type:
Project Value:
Toronto, Ontario
McGregor Allsop
May 2020
$140,000
Stipulated Sum
$140,000
This project consisted of installing a new main tank and a new day tank to the existing diesel generator complete with new fuel pump, piping, electrical, controls and new service platform. Commissioning of the project included a first fill, TSSA inspection, an OBT-1 inspection and a load bank test. As the prime contractor, Sprint was also responsible for the installation of the new chain link fence and bollard to protect the tank.